The diamond grinding portion of both S 11th Ave W and E 17th St S is complete. Henriksen Contracting is planning to start sawing and sealing tomorrow on S 11th Ave W, we will put out the no parking signs today. Henriksen Contracting plan to put out type II barricades with road closed to thru traffic on both ends of S 11th Ave W project, but still allow local traffic thru at all times.
E 17th St S sawing and sealing is expected to start no earlier than Wednesday July 12th , traffic will be delayed at times with flaggers, but will not closed at any time.