The second phase of construction for the Iowa Speedway Drive restoration project is scheduled to start on Wednesday, October 3.
The remaining work on the project is scheduled for 15 working days. Depending upon rain and wet weather, the project duration may be more than 3 weeks. During the phase of construction, Iowa Speedway Drive will be closed to traffic between the south side of Wal-Mart and S 13th Avenue E. Detour signs will route traffic along 1st Avenue E, E 12th Street S and S 13th Avenue E.
For more information, please reach out to the City of Newton Community Services division at (641) 792-6622.